Project Progress Update: Horace Mann School
WLC Architects, Inc.
 
WLC Architects continues its progress on the Horace Mann Additions and Renovation project.
 
Auditorium Building Renovation: WLC delivered the Design Development Package to Bernards on June 15, 2012. Bernards has begun their review of the DD package. Completion of District review comments of the DD package is expected in the next two to three weeks. WLC received design approval from DSA on April 24, 2012. Bids were received and opened on June 21, 2012. The apparent low bidder appears to be Minco. Bernards is currently verifying Minco’s bid documents. The General contractor will commence interior demolition and reconstruction upon receipt of School Board approval of bid. The Auditorium will be closed for a few months while the construction activity is underway.
 
Existing Building Renovation: WLC delivered the Design Development Package to Bernards on June 15, 2012. Bernards has begun their review of the DD package. Completion of District review comments of the DD package is expected in the next two to three weeks.
 
New Classroom Wing: WLC presented the REVIT model to the FAC and COC on June 13, 2012. WLC delivered the Design Development Package to Bernards on June 15, 2012. Bernards has begun their review of the DD package. Completion of District review comments of the DD package is expected in the next two to three weeks. This two-story building will stand at the corner of Charleville and Robertson and will include a new Multi-Purpose Room along with classrooms and labs for grade levels 1 through 8. The building also includes a level of subterranean parking.
 
Site Work: WLC delivered the Design Development Package to Bernards on June 15, 2012. Bernards has begun their review of the DD package. Completion of District review comments of the DD package is expected in the next two to three weeks. The Design Team has begun coordinating with the City of Beverly Hills on the design and extent of improvements that will be proposed for the surrounding street frontages. The Site Work construction will begin with the demolition of the existing Rotunda and Middle School wings. This final construction phase will follow the construction/renovation phases described above and will complete the school’s transformation.