Oil Well Plugging Project - BHHS » Project Map and Details

Project Map and Details

  • Location: Southwest corner of BHHS campus
  • Start Date: Late March 2018
  • Duration: Approximately 9 to 12 months
  • Work to be completed: Capping Existing 19 Wells; Removal of Underground Tubing, Pump Rods and Pumps; Cement Fill of 8,ooo ft. Depth of Wells; Derrick Removal
  • Safety Precautions:
    • FENCING: 8 ft. Screened Construction Fence 
    • SETBACK BARRIER: 180 ft.
  • Campus Impacts: Temporary Closure of Girls’ Softball Field